Delhi–Dehradun expressway misses July deadline? Here’s why commuters are angry with NHAI
Delhi Dehradun expressway has missed many deadlines and is far from completion. Very poor project management by @NHAI_Official .
— 🇮🇳 DK Sardana 🇮🇳 (@dksardana) July 16, 2025
Will @nitin_gadkari inform us when will this project be completed and open for public?@PMOIndia
Why Delhi–Dehradun expressway is still incomplete?
Despite most construction being completed, a key bottleneck remains—a 1,600 square meter land parcel in Mandola, Ghaziabad, stuck in legal disputes. The house on this plot, owned by Veersen Saroha’s family, has been under litigation since the 1990s. The Supreme Court has recently intervened, urging quicker resolution.
Other setbacks include a pillar collapse in Saharanpur, minor technical issues, and some local resistance, slowing down final clearances. However, officials say the majority of the work is done.
Sir Delhi Dehradun expressway me itna gehra gaddha ho gaya hai ki contractor ki gand usme sama jaye aapke meherbaani aur dedication ki badaualat se roz ek naya road toot ta hai iss desh me, aur fir aap media pe itne confidence se kuch bhi out of the world baatein karte ho 🍕🍔🍌
— NurseSeeSeaStick (@Elixxire) July 14, 2025
Commuters demand answers as frustration grows
On X, several citizens voiced their anger at NHAI’s poor management. The repeated delays in the Delhi–Dehradun Expressway have sparked widespread frustration among daily commuters. People are voicing their anger over NHAI’s handling of the project, pointing to poor planning, lack of transparency, and rising inconvenience.
Dehradun was earlier connected by a direct slow express train with Mumbai. Instead of replacing it with a better train, it’s discontinued denying service to many intermediate stations with Dehradun. @pushkardhami needs to get this fixed https://t.co/eQ3zdNadnU
— Pramod Tyagi (@PramodKTyagi) July 14, 2025
Many are tired of the constant traffic jams, especially in key areas like Geeta Colony and Karawal Nagar, and are urging authorities to open completed stretches without further delay. Citizens are questioning how such an important project can be allowed to stall for so long.
What Delhi Dehradun expressway offers when completed?
Once operational, the expressway will include six lanes, 113 underpasses, 5 railway overbridges, and 76 km of service roads. It features 16 interchanges for smooth access and a 340-meter tunnel at Datkali in Dehradun.
World class infra by our Engineers. This is the newly constructed Delhi Dehradun expressway.@khurpenchhpic.twitter.com/TkEaAa6Kin
— Ankush Tyagii 🇮🇳 (@14AnkushTyagi) July 9, 2025
Its most innovative feature is the 12-km elevated wildlife corridor over Rajaji National Park—Asia’s longest—designed to protect animals while promoting fast travel.
NHAI’s update: When will it really open?
Regional NHAI officer Mohammed Saifi and Union Minister Harsh Malhotra have stated that final testing is in progress and the expressway is nearly ready. Barring legal hold-ups, they expect it to open by August 2025.
But, commuters remain skeptical. One user asked on X: “Sir, when will the inauguration of the Delhi Dehradun expressway be?”
The project has been praised for balancing infrastructure and environmental protection. Its wildlife corridor and underpasses are designed to minimise ecological impact, a model other projects may follow.
Will this Delhi-Dehradun expressway live up to expectations?
Public trust is wearing thin, but NHAI officials insist that the Delhi-Dehradun expressway will be fully operational soon. Once launched, it will transform regional travel and set new benchmarks in sustainable highway construction.
For the latest and more interesting financial news, keep reading Indiatimes Worth. Click here.
By Shivani Kumari
By Shivani Kumari
By Shivani Kumari
By Karen Noronha
By Sneha Kumari
By Iraa Paul
By Iraa Paul